THE DUPLICATION OF THE RODOVIA DO SOL
(HIGHWAY) 28 KM AND IMPLANTATION OF
THE GUARAPARI RING ROAD 27 KM

Main Services Provided

Cleaning, deforestation and clearing

  • of 1.610.000m²

Excavation, loading and transportation

  • of 2.188.974m³ of 1st, 2nd and 3rd-rate material

HMA (Hot Mix Asphalt) Paving

  • 100.000 tons

Construction of bridges, overpasses and underpass walkways

  • of HMA Paving

Construction of toll booths